A project consists of the following four activities with activity times in days: Table 9.3
A project consists of the following four activities with activity times in days: Table 9.3   Using Table 9.3,the earliest finish (EF) time for activity C is A) 4 days. B) 6 days. C) 10 days. D) 11 days. Using Table 9.3,the earliest finish (EF) time for activity C is


A) 4 days.
B) 6 days.
C) 10 days.
D) 11 days.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q12: A Gantt chart provides a visual display

Q15: The following table of probabilistic time estimates

Q17: In general,projects are subject to less uncertainty

Q48: The slack time for an activity can

Q54: The three major components of project management

Q64: A _ breaks down a project into

Q65: Issues of cultural diversity in project management

Q80: Briefly discuss project management and what it

Q96: Management and control of a companywide portfolio

Q98: The key elements of project control includes

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines