Multiple Choice
A project consists of the following four activities with activity times in days:
Table 9.3
-Using Table 9.3,the earliest start (ES) time for activity B is
A) 5 days.
B) 6 days.
C) 11 days.
D) 14 days.
Correct Answer:

Verified
Correct Answer:
Verified