As Part of Its Quality-Improvement Program,a Company Is Conducting a Time

Question 18

Multiple Choice

As part of its quality-improvement program,a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element.An allowance factor of 16% is assumed. As part of its quality-improvement program,a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element.An allowance factor of 16% is assumed.   The normal cycle time for this job would be A) 1.809 minutes. B) 2.098 minutes. C) 1.530 minutes. D) 2.233 minutes. The normal cycle time for this job would be


A) 1.809 minutes.
B) 2.098 minutes.
C) 1.530 minutes.
D) 2.233 minutes.

Correct Answer:

verifed

Verified