Multiple Choice
Which of the following is not a potential risk associated with a project?
A) huge swings in resource requirements
B) extensive learning curve benefits
C) limited learning curve benefits
D) small swings in resource requirements
Correct Answer:

Verified
Correct Answer:
Verified