Multiple Choice
Construction of the shopping centre was to be completed by October 15 (late penalties were included in the contract) and tenants such as FabricLand would move in by November 1.However,the contractor for the shopping centre was 43 days late in completing and now FabricLand is suing the shopping centre owner for ________ damages,and the shopping centre owner is suing the contractor for ________ damages.
A) expectation; liquidated
B) expectation; consequential
C) consequential; reliance
D) general; liquidated
E) general; consequential
Correct Answer:

Verified
Correct Answer:
Verified
Q86: Which of the following is NOT an
Q87: Jack has a contract to deliver goods
Q88: An injured party may have several remedies
Q89: Peevyhouse v.Garland Coal & Mining Company is
Q90: Rachel had been looking forward to her
Q92: An injured party cannot elect to treat
Q93: Troy Feldmon agreed to purchase a house
Q94: A liquidated damages clause will not always
Q95: A party to a contract may break
Q96: Even if the wording of an exemption