Solved

Construction of the Shopping Centre Was to Be Completed by October

Question 91

Multiple Choice

Construction of the shopping centre was to be completed by October 15 (late penalties were included in the contract) and tenants such as FabricLand would move in by November 1.However,the contractor for the shopping centre was 43 days late in completing and now FabricLand is suing the shopping centre owner for ________ damages,and the shopping centre owner is suing the contractor for ________ damages.


A) expectation; liquidated
B) expectation; consequential
C) consequential; reliance
D) general; liquidated
E) general; consequential

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions