Multiple Choice
Onar Development stopped progress payments to its general contractor,Shape Construction.Upon the advice of their lawyer,Shape decided to sue for rescission of the contract rather than collect damages for breach.Shape will most likely
A) collect under quantum meruit.
B) ask for specific performance.
C) get expectation damages.
D) file for bankruptcy.
E) get an injunction.
Correct Answer:

Verified
Correct Answer:
Verified
Q26: B.C.Metal Works agreed to purchase steel rod
Q27: Give an example of damages that flow
Q28: In an action to enforce a covenant
Q29: Name two equitable remedies.Describe three ways in
Q30: In rare circumstances courts have awarded punitive
Q32: Give an example of a business mitigating
Q33: It is contrary to public interest to
Q34: In a contract of sale,where the seller
Q35: Explain the circumstances under which a claim
Q36: An award of damages<br>A)seldom comes out of