Multiple Choice
L contracted with M for the supply and installation of building materials and the renovation of M's property.L made certain payments,but refused to pay the balance because of defects in the workmanship.Evidence indicated that M had substantially completed the contract.In this case
A) the contract is at an end.
B) L substantially performed the contract.
C) M is entitled to damages for breach of contract valued at the cost of remedying the defects in workmanship.
D) the contract is an entire contract.
E) all of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q27: A clause entitling an employer to dismiss
Q28: A contract that is discharged by performance
Q29: Munson Fixtures Inc.has contracted with Weibe Installations
Q30: John and Sally enter into a contract
Q31: Julie was told by ComputerLand that if
Q33: A frustrating event is one that was
Q34: An agreement by parties to a contract
Q35: A company that installs heavy equipment is
Q36: A agrees to build a machine for
Q37: A agrees in writing to sell to