The network diagram below shows the five tasks required to complete a project and the associated times for those tasks. The network diagram below shows the five tasks required to complete a project and the associated times for those tasks.   Which of the following identifies the critical path tasks? A) A,B,D,F B) A,B,C,D,E,F C) A,B,E,F D) A,C,E,F Which of the following identifies the critical path tasks?


A) A,B,D,F
B) A,B,C,D,E,F
C) A,B,E,F
D) A,C,E,F