Multiple Choice
A company that had been using single sourcing decided to add a second supplier for one of its key raw materials.Which supply management goal does this BEST accomplish?
A) Fostering sustainability.
B) Reducing total costs.
C) Identifying,assessing,and mitigating supply chain risk.
D) Accessing technology and innovation.
Correct Answer:

Verified
Correct Answer:
Verified