Multiple Choice
A company must make 400 units per day.The company has one 12-hour shift.What is the efficiency if the total time to complete all tasks is 23 minutes and the company is using 18 workstations?
A) 22 percent
B) 71 percent
C) 50 percent
D) 88 percent
Correct Answer:

Verified
Correct Answer: