    The Total Time That It Takes to Get One Unit
Solved

The Total Time That It Takes to Get One Unit

Question 9

Question 9

Multiple Choice

The total time that it takes to get one unit through a process is called:


A) Flow time
B) Cycle time
C) Throughput time
D) Wait time

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: Which two of the following effects directly

Q5: The following sequence shows four operations for

Q6: A bottleneck activity in a process is

Q7: Adam Smith described his company's process as

Q8: Inventory held due to bottlenecks in a

Q10: You walk into a hair stylist shop.All

Q11: Which of the following statements best differentiates

Q12: Which of the following is NOT a

Q13: Under Juran's Law,whenever a problem occurs,what percentage

Q14: Which of the following actions will NOT

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines