A Claim Edge in a Resource-Allocation Graph Indicates That

Question 29

Multiple Choice

A claim edge in a resource-allocation graph indicates that


A) a process has been allocated a resource.
B) a process may request a resource.
C) a process may release a resource that it has already been assigned.
D) a process has requested a resource.

Correct Answer: