Question 69

Question 69

Multiple Choice

On an activity diagram, what is used to show parallel activities?


A) an arrow
B) a synchronization bar
C) a swimlane
D) a diamond

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q64: Swimlanes are useful to show how the

Q65: Partitioning on an activity diagram is shown

Q66: Method overloading means that:<br>A) the same method

Q67: What is used to show time ordering

Q68: When classes are involved in inheritance, another

Q70: Which type of class acts as a

Q71: Which type of class cannot be directly

Q72: _ reduces programming labor by reusing common

Q73: A statechart diagram is created for:<br>A) a

Q74: List the diagrams included in behavioral diagrams.

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines