    The Longest Path Through a PERT Diagram Is Called
Solved

The Longest Path Through a PERT Diagram Is Called

Question 71

Question 71

Multiple Choice

The longest path through a PERT diagram is called:


A) slack time.
B) the precedent activity path.
C) maximum path time.
D) the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q66: Which of the following is concerned with

Q67: _ feasibility refers to projecting whether the

Q68: A functional norm is one that could

Q69: In an interview, which of the following

Q70: On a problem definition, _ are the

Q72: Economic feasibility deals with whether or not

Q73: An advantage of buying computer hardware is

Q74: Improvements to systems include all the following

Q75: Tangible benefits are advantages measurable in _

Q76: Which of the following is dependent upon

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines