Multiple Choice
When two or more concurrent tasks depend on a single prior task,each of the concurrent tasks is called a(n) _____.
A) successor task
B) discrete task
C) antecedent task
D) descendent task
Correct Answer:

Verified
Correct Answer:
Verified