Mauricio Estimates That the First Module of the Project Could

Question 2

Multiple Choice

Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days,but most likely will require 20 days.What is the 20 day estimate called?


A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) logistical estimate (L)

Correct Answer: