Multiple Choice
Better Houses,Inc.has been contracted to build an addition on the Joyners' house.It built half of the addition and then unexpectedly announced that it was not going to finish the job.Better Houses' decision to stop the job is called a(n) :
A) constructive breach of contract.
B) substantial performance.
C) abandonment of contractual obligations.
D) repudiation of contract.
Correct Answer:

Verified
Correct Answer:
Verified