Solved

The Following Table Shows the Expected Value and Variance for 5

Question 36

Multiple Choice

The following table shows the expected value and variance for 5 projects a firm can undertake.  Project Expecled Value Variance A$100$124B$220$110C$100$138D$100$138E$200$124\begin{array} { c c c } \text { Project} & \text { Expecled Value} & \text { Variance } \\A & \$ 100 & \$ 124 \\B & \$ 220 & \$ 110 \\C & \$ 100 & \$ 138\\D & \$ 100 & \$ 138 \\E & \$ 200 & \$ 124\end{array} Which of the following is (are) correct if the mean-variance rule is used for the decision?


A) Project C is preferable to A.
B) Project E is preferable to B.
C) Project D is preferable to C.
D) all of the above
E) none of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions