Multiple Choice
The difference between the actual price and the standard price,multiplied by the actual quantity of materials purchased,is the:
A) direct materials spending variance.
B) direct materials volume variance.
C) direct materials price variance.
D) direct materials quantity variance.
Correct Answer:

Verified
Correct Answer:
Verified