Multiple Choice
Swan Company has a direct labor standard of 15 hours per unit of output.Each employee has a standard wage rate of $14 per hour.During March,employees worked 13,100 hours.The direct labor rate variance was $9,170 favorable,and the direct labor efficiency variance was $15,400 unfavorable.How many units were produced?
A) 873 units
B) 655 units
C) 1,100 units
D) 800 units