Multiple Choice
The difference between actual volume and budgeted production,multiplied by the fixed overhead rate based on practical capacity,is the:
A) expected (planned) capacity variance.
B) unexpected (unplanned) capacity variance.
C) total capacity variance.
D) volume variance.