Multiple Choice
Beech has budgeted fixed overhead of $202,500 based on budgeted production of 13,500 units.During July,14,100 units were produced and $214,200 was spent on fixed overhead.What is the fixed overhead volume variance?
A) $11,700 unfavorable
B) $1,800 unfavorable
C) $1,800 favorable
D) $9,000 favorable
Correct Answer:

Verified
Correct Answer:
Verified