Essay
Regent Corp.uses a standard cost system to account for the costs of its one product.Materials standards are 3 pounds of material at $14 per pound,and labor standards are 4 hours of labor at a standard wage rate of $11.During July Regent Corp.produced 3,300 units.Materials purchased and used totaled 10,100 pounds at a total cost of $142,650.Payroll totaled $146,780 for 13,150 hours worked.Calculate the:
a.direct materials price variance.
b.direct materials quantity variance.
Correct Answer:

Verified
a.$1,250 unfavorable = $142,650 - (10,10...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q90: A quantity standard is:<br>A)the total dollar amount
Q91: Bonnie Company has a direct labor standard
Q92: Raven applies overhead based on direct labor
Q93: The difference between the actual labor hours
Q94: The direct materials quantity variance is the
Q96: Benjamin Inc.uses a standard cost system and
Q97: Wilson Manufacturing has provided you with the
Q98: An ideal standard is one that can
Q99: The difference between the actual fixed manufacturing
Q100: Beech has budgeted fixed overhead of $202,500