The Probability Based Scheduling Approach That Recognizes and Measures the Uncertainty

Question 66

Multiple Choice

The probability based scheduling approach that recognizes and measures the uncertainty of the project completion times is the


A) GANTT chart.
B) PERT chart.
C) Critical Path Method.
D) GERT chart.
E) none of the above.

Correct Answer: