Tanouye Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:  Hours  Wait time 12.7 Process time 1.6 Inspection time 0.4 Move time 2.1 Queue time 8.8\begin{array}{lr} & \text { Hours } \\\text { Wait time } & 12.7 \\\text { Process time } & 1.6 \\\text { Inspection time } & 0.4 \\\text { Move time } & 2.1 \\\text { Queue time } & 8.8\end{array} The throughput time was:


A) 4.1 hours
B) 12.9 hours
C) 25.6 hours
D) 21.5 hours