Dubberly Corporation's cost formula for its manufacturing overhead is $30,600 per month plus $64 per machine-hour. For the month of March, the company planned for activity of 7,900 machine-hours, but the actual level of activity was 7,880 machine-hours. The actual manufacturing overhead for the month was $558,610.The manufacturing overhead in the planning budget for March would be closest to:
A) $534,920
B) $558,610
C) $536,200
D) $560,028
Correct Answer:

Verified
Correct Answer:
Verified
Q415: Rameriz Corporation is a shipping container refurbishment
Q416: Bracken Clinic uses client-visits as its measure
Q417: Standahl Air uses two measures of activity,
Q418: Korsak Corporation is a service company that
Q419: Dreckman Corporation is a service company that
Q421: Ruge Clinic bases its budgets on the
Q422: Pickrel Corporation is an oil well service
Q423: Varriano Corporation bases its budgets on the
Q424: A favorable spending variance occurs when the
Q425: Poling Clinic bases its budgets on the