Construction of the Shopping Centre Was to Be Completed by October

Question 22

Multiple Choice

Construction of the shopping centre was to be completed by October 15th (late penalties were included in the contract) and tenants like FabricLand would move in by November 1st. However, the contractor for the shopping center was 43 days late in completing and now FabricLand is suing the shopping centre owner for _ damages, and the shopping center owner is suing the contractor for damages.


A) consequential; reliance
B) general; consequential
C) expectation; consequential
D) expectation; liquidated
E) general; liquidated

Correct Answer: