Multiple Choice
Construction of the shopping centre was to be completed by October 15th (late penalties were included in the contract) and tenants like FabricLand would move in by November 1st. However, the contractor for the shopping center was 43 days late in completing and now FabricLand is suing the shopping centre owner for _ damages, and the shopping center owner is suing the contractor for damages.
A) consequential; reliance
B) general; consequential
C) expectation; consequential
D) expectation; liquidated
E) general; liquidated
Correct Answer:

Verified
Correct Answer:
Verified
Q17: Jack's supplier fails to deliver the products
Q18: Working on a firm order, Henry tried
Q19: Casey Construction abandoned its $23 million north
Q20: Nominal damages are<br>A) assessed where a party
Q21: Ralph ordered the installation of a satellite
Q23: Prompt Delivery Ltd. operates a delivery service
Q24: What is the purpose of an award
Q25: B.C. Metal Works agreed to purchase steel
Q26: The Lockheart Community has a restrictive covenant
Q28: In an action to enforce a covenant