Question 7

Multiple Choice

Lambhair Corp. contracted with Prof. Jones for a two week series of seminars with employees in the Appliance Division. Prof. Jones put in ten days of specific preparation only to have the series cancelled at the Appliance Division and rescheduled at the Tool Division. This change required Prof. Jones to put in another five days of specific preparation. This change was a breach of the original contract. Prof. Jones is entitled to what type of damages?


A) nominal
B) reliance
C) consequential
D) general
E) expectation