Multiple Choice
A and B enter into a contract whereby A agrees to supply B with 10,000 tins of tuna at the rate of 1000 tins per month from his tuna factory in Bayport, Nova Scotia, and B agrees to pay A $2 per tin. A supplies 1000 tins of tuna and before he can collect, his factory is destroyed by fire. If the contract is discharged by frustration, which of the following statements is correct?
A) All obligations under the contract are discharged, A and B's obligations are both discharged, and B does not have to pay A the sum of $2,000.
B) B will not have to pay A the sum of $2,000 because there is no longer a contract.
C) Only future obligations are discharged and B must pay A the sum of $2,000.
D) A must obtain the tuna from another source to satisfy the contract.
E) B will have to pay A the sum of $2,000 because there was no deposit.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: A debtor who makes an unsuccessful but
Q34: An agreement by parties to a contract
Q38: Where the required elements for frustration in
Q46: A frustrating event is one that cannot
Q47: A unilateral contract is discharged by performance
Q48: Julie was told by ComputerLand that if
Q52: A novation agreement is only effective if<br>A)
Q53: Park- Lot Maintenance Corp. entered into a
Q54: While traveling in the U.S., Joey bought
Q56: The Frustrated Contracts Act determines:<br>A) how expenses