Question 41

Multiple Choice

A site manager has three day laborers available for eight hours each and a burning desire to maximize his return on their wages.The site manager uses linear programming to assign them to two tasks and notes that he has enough work to occupy 21 labor hours.The linear program that the site manager has constructed has


A) slack.
B) surplus.
C) a positive shadow price for labor.
D) no feasible solution.