The Production Schedule for a New Product Follows Month 1234 No Units 15204035
Question 42
Question 42
Multiple Choice
The production schedule for a new product follows Month 1234 No Units 15204035 The first unit took 100 hours to complete, and the rate of learning is 80 percent. Each employee works 40 hours per month. Refer to the copy of Table G.1 below. Conversion Factors for the Cumulative Average Number of Direct Labor Hours per Unit 80% Learning Rate ( n= cumulative production) n1234567891011121314151617181.000000.900000.834030.785530.747550.716570.690560.668240.648760.631540.616130.602240.589600.578020.567370.557510.548340.53979n1920212223242526272829303132333435360.537180.524250.517150.510450.504100.498080.492340.486880.481670.476680.471910.467330.462930.458710.464640.450720.446940.44329n37383940641282565126007008009001,0001,2001,4001,6001,8002,0000.439760.436340.433040.429840.373820.302690.244050.196220.186610.177710.170340.164080.158670.149720.142540.136600.131550.1272090% Learning Rate ( n= cumulative production) n1234567891011121314151617181.000000.950000.915400.889050.867840.850130.834960.821720.809980.799450.789910.781200.773200.765800.758910.752490.746460.74080n1920212223242526272829303132333435360.735450.730390.725590.721020.716660.712510.708530.704720.701060.697540.694160.690900.687750.674710.681770.678930.676170.67350n37383940641282565126007008009001,0001,2001,4001,6001,8002,0000.670910.668390.665950.663570.620430.560690.505860.455940.445190.434960.426290.418780.412170.400970.391730.383900.377110.37114
-Using the information in Case G.1,how much time will it take to produce the units in month 1?
A) Fewer than 800 hours B) Greater than or equal to 800 hours but fewer than 1,100 hours C) Greater than or equal to 1100 hours but fewer than 1,500 hours D) Greater than 1,500 hours
Correct Answer:
Verified
Unlock this answer now Get Access to more Verified Answers free of charge