Multiple Choice
Table 4.2
High Tech, Inc. is producing two types of products: A and B. Both are produced at the same sawing operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic) . The demand forecasts, batch sizes (units/batch) , processing times (hr/unit) , and setup times (hr/batch) follow.
The sawing machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 10 percent capacity cushion.
-Using the information from Table 4.2,how many hours of capacity can the company expect from each of its sawing machines?
A) less than 3500 hours
B) more than 3500 hours but less than 3700 hours
C) more than 3700 hours but less than 3900 hours
D) more than 3900 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q25: Economies of scale is a concept that
Q27: Table 4.3<br>The North Bend Manufacturing Company
Q30: Which one of the following statements about
Q62: Utilization is calculated as the ratio of
Q63: Explain the cost and time implications that
Q66: A bottleneck is an operation that has
Q71: Waiting line models are often used for
Q92: The maximum output that can reasonably be
Q101: A capacity cushion is the amount of
Q137: In a dental office, measuring capacity based