Multiple Choice
When mixed model scheduling is used on an assembly-line
A) large lot sizes are the result.
B) JIT is not possible.
C) nonuniform workload will result in the feeding of work centres.
D) a uniform workload will result in the feeding of work centres.
Correct Answer: