Multiple Choice
Table 7.1
A toy company uses a kanban system to make a metal fastener that is a component of several toys. The waiting time for a container of the fasteners during production is 0.25 day; average processing time is 0.15 day per container. Each container holds 200 fasteners. The company uses 2000 fasteners a day in the production of its product.
-Use the information in Table 7.1.Using an efficiency factor of 5 %,calculate the number of kanban containers needed for the fastener.
A) 3 or less
B) 4 or 5
C) 5 or 6
D) the next person or machine to use or further the current process 7 or more
Correct Answer:

Verified
Correct Answer:
Verified
Q21: The quality management tool called poka-yoke is
Q32: What are the characteristics of just- in-
Q42: Which one of the following is not
Q44: Which of the following statements regarding a
Q46: Suppliers often cite which of the following
Q48: Which one of the following is not
Q56: Hidden problems are generally uncovered during the
Q69: If any employee senses that the process
Q131: The Japanese word for card that has
Q133: Just- in- time systems do not need