Multiple Choice
Table 3.7
-Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become?
A) 0 weeks
B) 1 or 2 weeks
C) 3 or 4 weeks
D) 5 or 6 weeks