Multiple Choice
Table 3.9
All activity times for the project are in weeks.
-Using Table 3.9,what is the critical path of this project?
A) A-C-F-H
B) B-D-F-H
C) B-D-G
D) B-E-G
Correct Answer:

Verified
Correct Answer:
Verified