You Are Responsible for Managing a Project with the the

Question 29

Multiple Choice

Table 3.11
You are responsible for managing a project with the
following activities (times are given in days) .
 Activity  Expected  Time  Immediate  Predecessor(s)   A 3 B 6 C 2 D 5 A  E 2 C  F 7 A  G 4 B,D,E \begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 3 & \cdots \\\text { B } & 6 & - \cdots \\\text { C } & 2 & \cdots \\\text { D } & 5 & \text { A } \\\text { E } & 2 & \text { C } \\\text { F } & 7 & \text { A } \\\text { G } & 4 & \text { B,D,E } \\\hline\end{array}
-Using,Table 3.11,what is the critical path and expected completion time for this project?


A) A-F; 12 days
B) A-D-G; 12 days
C) B-G; 10 days
D) C-E-G; 8 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions