Multiple Choice
Table 3.11
You are responsible for managing a project with the
following activities (times are given in days) .
-Using,Table 3.11,what is the critical path and expected completion time for this project?
A) A-F; 12 days
B) A-D-G; 12 days
C) B-G; 10 days
D) C-E-G; 8 days
Correct Answer:

Verified
Correct Answer:
Verified
Q1: The critical path is the sequence of
Q25: If a project has multiple critical paths,which
Q27: Explain how cost-time tradeoffs should be analyzed