Multiple Choice
Which one of the following statements concerning typical objectives of production and staffing plans is best?
A) Improved on-time delivery also means minimizing inventory investment.
B) Minimizing costs will also minimize changes in the workforce levels.
C) Maximizing profits also minimizes inventory investment.
D) Adjusting workforce levels may cause lower productivity because new employees typically need time to become fully productive.