Multiple Choice
Table 11.1
Gable Express Co. provides delivery service seven days a week.
The daily requirements (in workers) are estimated as follows:
Each worker is required to work five days per week,
and each must have two consecutive days off.
-Use the information in Table 11.1.What is the minimum number of workers required if preference is given to the pair S-Su in case of a tie in the selection of off days?
A) less than 8 workers
B) 8 workers
C) 9 workers
D) greater than 9 workers
Correct Answer:

Verified
Correct Answer:
Verified