Multiple Choice
Planned lead time for purchased items is
A) setup time plus processing time plus waiting time.
B) setup time plus materials handling time plus waiting time.
C) time difference between when the order was issued and when it would be received from the supplier.
D) order processing time.
Correct Answer:

Verified
Correct Answer:
Verified