Multiple Choice
Which of the following statements about MRP is TRUE?
A) MRP always recognizes capacity limitations in production as well as human resources.
B) MRP recognizes the capacity limitations in production, but not in human resources.
C) Capacity limitations are implicit in all MRP calculations.
D) MRP may generate a planned order release that exceeds current production capacity.
Correct Answer:

Verified
Correct Answer:
Verified