Use the following MRP record to answer the question.
What are the quantities of planned order releases for item DEF for the first five weeks (weeks 1,2,3,4,and 5) ?
A) 30, 0, 60, 0, 145
B) 60, 0, 145, 0, 0
C) 0, 30, 60, 0, 0
D) 30, 0, 60, 145, 0