Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s) .
Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
-Use the information in Table 13.3.Which one of the following statements about item C is TRUE?
A) It has a planned receipt of 80 units in week 3.
B) Its second planned order release is for 200 units in week 3.
C) It has a planned receipt of 180 units in week 6.
D) Its first planned order release is for 130 units in week 1.
Correct Answer:

Verified
Correct Answer:
Verified
Q11: MRP can be used to best advantage
Q25: For items manufactured in- house, one component
Q50: Table 13.7<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5515/.jpg" alt="Table 13.7
Q60: Using a periodic order quantity generates a
Q86: _ systems are large, integrated information
Q89: _ demand occurs because the quantity
Q99: An action bucket is the first week's
Q114: In MRP, a(n) _ is an item
Q143: Faster response to market changes and reduced
Q155: Explain why MRP does a better job