Multiple Choice
Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s) .
Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
-Use the information in Table 13.3.Which one of the following statements about item E is TRUE?
A) There will be an action notice to expedite the scheduled receipt up to week 2.
B) There is a planned receipt of 250 units in week 2.
C) There is one planned receipt for the next 6 weeks.
D) There is a planned order release of 250 units in week 3.
Correct Answer:

Verified
Correct Answer:
Verified
Q26: Table 13.6<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5515/.jpg" alt="Table 13.6
Q38: Projected _ inventory is an
Q39: Discuss the differences and similarities among material
Q55: An item is called a dependent demand
Q61: The principles of MRP should not be
Q109: For items manufactured in- house, one component
Q111: MRP is generally practiced on items emanating
Q122: Table 13.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2786/.jpg" alt="Table 13.5
Q130: Table 13.3<br>Consider the following MPS, BOM,
Q134: The master production schedule (MPS) details how