Solved

Table 134
Consider the MPS, BOM and Inventory Data Shown Below

Question 66

Multiple Choice

Table 13.4
Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities.
Week
 Week 123456 MPS 8080\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { MPS } & & & 80 & 80 & & \\\hline\end{array}
Bill of Material
-Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B.
-Subassembly B uses 1 each of component D.
Selected Inventory Data Item
 Table 13.4 Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities. Week  \begin{array} { | c | c | c | c | c | c | c | }  \hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline \text { MPS } & & & 80 & 80 & & \\ \hline \end{array}  Bill of Material -Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B. -Subassembly B uses 1 each of component D. Selected Inventory Data Item    -Use the information in Table 13.4. When does the first planned order release for item C occur? A)  Week 1 or 2 B)  Week 3 C)  Week 4 D)  No planned order releases needed

-Use the information in Table 13.4. When does the first planned order release for item C occur?


A) Week 1 or 2
B) Week 3
C) Week 4
D) No planned order releases needed

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge