Multiple Choice
Table 13.4
Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B.
-Subassembly B uses 1 each of component D.
Selected Inventory Data Item
-Use the information in Table 13.4. When does the first planned order release for item C occur?
A) Week 1 or 2
B) Week 3
C) Week 4
D) No planned order releases needed
Correct Answer:

Verified
Correct Answer:
Verified
Q15: Part commonality tends to increase inventory costs.
Q61: The principles of MRP should not be
Q62: Material requirements planning II allows MRP to
Q63: Which of the following statements about MRP
Q67: Complete the following MRP schedule: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5515/.jpg"
Q68: In an MRP system, from what sources
Q69: Complete the following MRP schedule: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5515/.jpg"
Q70: Use the following MRP record to answer
Q74: MRP II ties MRP to the company's
Q96: MRP _ is a process that converts