Multiple Choice
Table 13.8
Sunshine Manufacture produces three products, X, Y, and Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A, each component of C is manufactured from one unit of B. End item Z is assembled from one unit of D and one unit of C, D is manufactured from one unit of A, and C is manufactured from one unit of B.
-Use the information in Table 13.8.If item C has a manufacturing lead time of two weeks and a planned receipt of 65 units is needed in week 4,which of the following statements is TRUE?
A) The planned order release in week 2 for item C is 130 units.
B) The gross requirements for item B in week 4 are at least 65 units.
C) The gross requirements for item B in week 2 is 130 units.
D) The gross requirements for item B in week 2 is 65 units.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Table 13.7<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5515/.jpg" alt="Table 13.7
Q42: A periodic order quantity issues orders at
Q50: The action notice is a<br>A) document that
Q53: Use the following MRP record to answer
Q55: One of the differences between Enterprise Resource
Q78: The aggregate plan, derived from the master
Q105: An item made from water more components
Q126: An enterprise process is a company- wide
Q129: A material requirements plan for each component
Q136: Part commonality refers to the degree to