NPV Analysis on a New Project Has Been Carried Out

Question 19

Multiple Choice

NPV analysis on a new project has been carried out to identify the crude NPV and the NPV of the expansion option. Which other three types of analysis should be carried out?


A) NPV of taking no action
B) NPV of the abandonment option
C) NPV of the timing option
D) NPV of other option possibilities

Correct Answer: