Multiple Choice
Which three the following steps would you complete when adjusting for risk through the discount rate?
A) Add a premium to the risk- free discount rate
B) Calculate net present value, based solely on the premium adjustment
C) Use the risk- adjusted discount rate to calculate net present value
D) Make decisions, based on a subjective judgement of the risk
Correct Answer:

Verified
Correct Answer:
Verified