Multiple Choice
The values of NPV for four projects have been calculated as follows: Project A = £11m; Project B = 0; Project C = - £5m; Project D = - £12m. Which of the projects would you suggest should be adopted?
A) Only Project A
B) Projects A and B
C) Project C and D
D) Projects B, C and D
Correct Answer:

Verified
Correct Answer:
Verified