A Behavioral Approach for Dealing with Project Risk That Uses

Question 23

Multiple Choice

A behavioral approach for dealing with project risk that uses several possible values for a given variable such as cash inflows to assess that variable's impact on NPV is called


A) none of the above.
B) simulation analysis.
C) sensitivity analysis.
D) scenario analysis.

Correct Answer: